Skip site navigation (1) Skip section navigation (2)

Section Navigation

FreeBSD 12.2 Release Process

Introduction

This is the release schedule for FreeBSD12.2. For more information about the release engineering process, please see the Release Engineering section of the web site.

General discussions about the pending release and known issues should be sent to the public freebsd-stable mailing list.

Help With The Next FreeBSD Release

Our developers and release engineers are working on the next release of FreeBSD; if you wish to help with testing, please download the latest build. Please note that these images are, by their very nature, intended for testing and should not be used in production environments.

Available installation images are listed on the download page.

Schedule

Action Expected Actual Description
Initial release schedule announcement - 3January2020 Release Engineers send announcement email to developers with a rough schedule.
Release schedule reminder 24July2020 17July2020 Release Engineers send reminder announcement e-mail to developers with updated schedule.
Code slush begins 28August2020 28August2020 Release Engineers announce that all further commits to the stable/12 branch will not require explicit approval, however new features should be avoided.
releng/12.2 branch 11September2020 11September2020 releng/12.2 branch created; future release engineering proceeds on this branch.
BETA1 builds begin 11September2020 11September2020 First beta test snapshot.
BETA2 builds begin 18September2020 18September2020 Second beta test snapshot.
BETA3 builds begin 25September2020 - Third beta test snapshot.
RC1 builds begin 2October2020 - First release candidate.
RC2 builds begin 9October2020 - Second release candidate.
RC3 builds begin* 16October2020 - Third release candidate.
RELEASE builds begin 23October2020 - 12.2-RELEASE builds begin.
RELEASE announcement 27October2020 - 12.2-RELEASE press release.
Turn over to the secteam - - releng/12.2 branch is handed over to the FreeBSDSecurity Officer Team in one or two weeks after the announcement.